High-Rise at Wilshire & Crescent Tops Out

One block west of the Miracle Mile in Los Angeles, Largo recently topped-out on a high-rise residential tower on the corner of Wilshire and Crescent Heights Blvd. Working with Matt Construction the high-rise building consists of 20 levels above grade and 3 levels below for a total of 393,137gsf. The building is designed by Steinberg Architects and Nabih Youssef Structural Engineers and features 150 apartment units, 7 levels of parking providing 411 stalls and a rooftop terrace complete with lounge, swimming pool, fire pit and a hot tub. Typical levels provide 10’6″ floor-to-floor heights while the level 17 penthouse and 18 skydeck are 14′ and 18′ respectively. The project also includes 6,000sf of retail space on the ground floor, a open space terrace at the back of the development and two levels of structural steel at the top housing MEP support facilities.

[print_gllr id=4906]

Project News

Paseo Colorado Retrofit

Largo is currently working on the seismic retrofit of a two level below grade precast concrete parking structure at the Paseo Colorado development in Pasadena. Located along South Los Robles Avenue between Historic Route 66 (Colorado Blvd.) and Green Street, the upgraded structure will provide support for the new commercial and hospitality space to be constructed above.

Largo’s team is busy drilling and epoxying dowels to expand footings and enlarge columns and using cast-in-place concrete to construct shear walls. With hundreds of corbels to be installed, a custom steel form was created so the team could efficiently pour these support structures. Foam inserts in the deck are being used to lighten the load along Green Street instead of a thickened slab where the structure connects to street level. Placing embeds for structural steel and forming and pouring a new vehicular ramp are also included in Largo’s scope. The work includes additional utility rooms, new pedestrian access stairs and elevators, and modified exhaust, lighting and fire protection systems. Working with general contractor CW Driver, Gonzalez Goodale Architects and Englekirk Structural Engineers, Largo’s scope is scheduled to be complete in early 2018.

[print_gllr id=5255]

Social Responsibility

Charity Golf Tournament with the Illumination Foundation

On July 31, Largo Concrete and the Sage Hill High School IF Club hosted a Charity Golf Tournament at the Pelican Hill Resort in Newport Coast. The proceeds benefited the Irvine based Illumination Foundation and their mission to “break the cycle of homelessness” in Southern California. With the help of Platinum Sponsors Associated Readymix, Holliday Rock, Millennium Reinforcing and San-Mar Construction, the event raised $275,000 for the charity! The organization provides a myriad of services from housing and workforce training to medical and recuperative care to those in need.