Linea Los Angeles Wins ACI Award for Decorative Uses of Concrete

The American Concrete Institute (ACI) gave the “Decorative Uses of Concrete Construction” award to the Linea Apartments in Los Angeles, CA. Click here to view a list of all the projects which received recognition at this years virtual event and check out the Linea project video below:

The Linea mid-rise luxury apartment complex is centrally located along Sepulveda Blvd. between Pico and Exposition in West Los Angeles. The 545,000gsf development features two levels of below grade parking, three levels of retail and commercial space starting at street level, and residential units from the podium deck up. A total of 911 parking stalls are provided for the 566 market rate and 66 affordable housing units. Residential space is spread out across one ten level and three five level structures rising from the podium. The boomerang shaped nine level structure is located toward the back of the podium and has post-tensioned slabs and a concrete moment frame with both upturned and downturned beams. The five level buildings are light gauge metal stud structures facing Sepulveda Blvd.

The 125,000sf of slab on grade area starts two levels below grade with 1,550CY of shotcrete applied to the perimeter and radial ramp walls of the subterranean parking levels. Due to rebar congestion shotcrete crews utilized a “hybrid method” to place the pilasters in the perimeter basement walls. This is accomplished by forming the pilaster with Stayform then pouring and vibrating readymix into the form without the air component. The Stayform is then removed and the surface is pneumatically applied and finished in the traditional shotcrete fashion. 14,000sf of 22’ tall decks are also featured in the podium structure where teams used Titan XL 625 posts for shoring. During the height of construction in the J-shaped shaped podium Largo had two boom pumps onsite utilizing four masts.

The podium plaza level features a landscaped courtyard with two pools and communal outdoor dining and recreation areas. The modern outdoor living space is decorated with 10,000sf of architectural board-formed concrete parapet walls and planters. The exposed concrete look is carried on to the courtyard roof deck on level ten of the cast-in-place structure, where more concrete benches and board-formed planters can be found lining another pool, a spa, daybeds and cabanas.

Designed by Van Tilburg, Banvard & Soderbergh Architects with Englekirk providing the structural engineering, the development opened during the summer of 2020. The penthouse currently rents for over $15,000/month with impressive views of the I-10 and I-405 interchange. Overall, Largo Concrete placed 53,200CY of concrete over 11 months. 73 elevated deck pours were accomplished over a 9.25-month duration averaging a pour ever 2.7 working days.

Ivy Station Wins ACI Award for Outstanding Performance in Design and Engineering

The American Concrete Institute (ACI) recently awarded the Ivy Station project the award for Outstanding Performance in Design and Engineering. Click here to view a list of all the projects which received recognition this year and check out the Ivy Station project video below:

The new development sits adjacent to the Culver / Venice Metro Line Station in Culver City, CA along Venice and Jefferson Blvd. This city-block-wide transit-oriented development is a true mixed-use project with a commercial office space, hospitality rooms and residential units with a retail plaza at street level. Each component sits atop a three level below grade, 607,000sf parking podium housing 1,538 stalls, 300 of which are dedicated to Metro riders.

The versatility of the podium is also depicted with three different building types rising from the 218,000sf plaza level lined with space for retail and food stores. The 148-room hotel utilizes structural steel while the 200 residential units are spread across wood frame. Both components are five stories tall sitting atop an elevated deck of concrete while the entire commercial building is cast-in-place concrete.

Over 23,600CY was placed for the 236,700sf mat foundation ranging from 17” to 60” thick three levels below the street. Largo utilized their own powerful City Pumps to hose the readymix hundreds of feet from the street down to the jobsite. Nearly 3,000CY of shotcrete walls were pneumatically placed around the perimeter of the basement parking levels. Interior structural walls up to 3’ thick enclose staircases and radial ramps giving pedestrians and vehicles access to the below grade parking.

At the plaza level, structural columns switch from rectangular to circular which juxtapose the angular shaped decks. Typical levels have a 13’8” floor-to-floor height with the first and fifth levels at 15’. The concrete columns, interior walls and soffits remain exposed throughout the commercial building to usher views outward to the street and plaza with a grand entrance off Venice reaching 28’5” in height. Largo worked with general contractor Bernards, KFA architects and Englekirk structure engineers to place 81,500CY of concrete over 14 months.

Natiivo Tower Tops Out at 48 East Avenue

Largo Concrete topped out at the Natiivo tower in downtown Austin, TX earlier this month. Located at the edge of the rapidly growing Rainey Street District, the 442,668gsf building is 33 levels all above grade. The first nine levels of the building are dedicated to parking with 24 levels of residential above holding 248 units.

All units come fully furnished with hotel licensing and can be offered as short-term rentals with building management providing hotel-like services and amenities. In addition to on-site concierge, housekeeping and laundry services the building also features a 18,000sf open air terrace on the 10th floor and a rooftop pool with cabanas and fireplace seating areas.

In total Largo poured 20,000CY of concrete over the course of 15 months with 130,000 manhours. The building is designed by STG Design and Cardno Haynes Whaley structural engineers and general contractor AECOM Hunt expect to have the project complete during the summer of 2021.

Reach for the Stars!

The New Century Plaza Towers became the tallest buildings in Century City, CA this month when Largo Concrete topped out at level 46. In addition to constructing the twin towers simultaneously, Largo also retrofitted the historic Fairmont Hotel designed by world-renowned architect Minoru Yamasaki along Avenue of the Stars. Yamasaki was also responsible for the triangular shaped 44-story Century Plaza Office Towers located on the opposite side of the main thoroughfare. In an effort to pay homage to Yamasaki, design architect Pei Cobb Freed & Partners shaped the new towers as reuleaux triangles. A figure consisting of three circular arches, formed from the intersection of three circular disks, each having its center on the boundary of the other two.

Largo began construction during the summer of 2018 by pouring seven large mat foundations, two of which were we over 9,300CY. Limited access to the site meant much of the readymix for the large pours had to be piped in from Constellation Way to placing booms mounted on tower crane foundations. The first of these two pours utilized five truck mounted boom pumps and two placing booms to place 9,509CY over the course of 16 hours. The second large pour was even further from the street and required five placing booms and two boom pumps to place 9,367CY over 16 hours.

The first four levels out of the ground are dedicated primarily to 1,345 parking stalls and back-of-house facilities. Radius vehicular ramps and grand staircases exude the circles used to shape the reuleaux tower decks to come above. A 25’ tall radius transfer beam supports 30 columns opening up the loading dock space. Formwork supplier Peri USA assembled a temporary access bridge to deliver rebar from Constellation Way to the back of the site. In addition to reducing the amount of crane time the temporary bridge also minimized vehicular traffic along the privately owned Solar Way.

The twin towers rise from the exquisitely landscaped plaza level lined with retail shops and cafés for a pedestrian experience which continues through the hotel lobby to Avenue of the Stars. The towers were constructed concurrently with crews pouring a deck on alternate towers every two days. A custom PERI ACS 400 core wall, self-climbing interior system with gantry beams suspending the exterior formwork was used for the hexagonal-shaped core walls. A radius trolley trailer beam was suspended from the core climber to facilitate construction of the steel framing inside the tower lobbies. The entire system weighed over 360,000lbs.

A column mounted cocoon screen with attached roll-back column formwork enclosed the upper floors as they were being constructed which removed re-shoring and enhanced safety on the site. The perimeter column forms were designed so that they could be stripped horizontally, from underneath the deck, which allowed the deck formwork to be completed before the column forms were poured and stripped. Largo also self-formed the masonry scope of work placing 102,000 concrete masonry units throughout the building including the entire height of the core.

In an effort to ease the strain on vertical transportation between the two towers, teams utilized a temporary 60’ pedestrian bridge spanning the two structures beginning at level 30 and moving up to level 43 as the buildings progressed. This proved especially helpful once Covid-19 reduced the number of individuals in each manlift for social distancing measures.

When complete, the $2.5 billion revitalization project will be over 1 million square feet on the 6.13-acre site. The Fairmont Century Plaza will feature 400 hotel suites with 63 private residences on the upper levels and the towers will hold 290 luxury condominiums with multi-level penthouses. Largo Concrete will have worked 760,000 Man Hours placing 151,000 CY of Concrete! General contractor Webcor is working with Gensler and Harley Ellis Devereaux Architects and structural engineer Englekirk to have the development open during the summer of 2021.

Yerba Buena Island Condominiums Top Out

Largo Concrete poured the last concrete deck at the Yerba Buena Island Condominiums this month. The project is perched on the small island in the San Francisco Bay best know for its tunnel connecting the two spans of the Bay Bridge. The development begins at the corner of Macalla and North Gate Roads on the northeast side of the island and works it’s way up the hill. The structure is 257,380gsf with 2.5 levels of below grade podium parking and five levels of light gauge metal stud above it. Largo worked with DCI Engineers to deliver the superstructure in a design-build format. Tenants will enjoy views of the self-anchored suspension eastern span of the Bay Bridge with Oakland and Emeryville in the background to the east, and Treasure Island to the north. General contractor Cahill Contractors are BDE Architecture aim to have the development open in early 2021.

Le Conté Apartments becomes UCLA’s Tallest Building

Largo Concrete topped out at the UCLA Le Conté Apartments this summer making it the tallest building on campus. The undergraduate student housing project is located at the corner of Le Conte and Gayley Avenue on the south side of the campus. The south building is 11 cast-in-place levels above grade and the north is 19. The overall project is 301,761gsf and will add 1,167 beds in 192 rooms. General contractor PCL Construction, Studios Architecture and Nabih Yousseff & Associates structural engineers are on track for temporary occupancy in the Winter of 2021.

Miro Towers Become the Tallest Buildings in San Jose

The Miro Towers became San Jose’s tallest structures this month when Largo poured level 29 at 291′ above street level! Located on the north side of E. Santa Clara Avenue between Fourth and Fifth, the buildings are across the street from City Hall which used to be the city’s second tallest structure. Miro will feature a total of 630 two and three bedroom units and 633 parking spaces.

Stressing Procedure

Transfer girders utilize four rows of post-tensioned cables which are progressively stressed throughout construction. The girders are located on level five above grade and are up to 72” wide by 64” deep! The additional rows of PT cables are spaced 6” apart and lay below a row of tendons which are stressed after placing level five. Upon completion of level ten the bottommost row is stressed, then the second from the bottom row is tensioned at level 15, ending at level 25.

Steinberg Hart Architects, DCI Structural Engineers, and general contractor Suffolk Construction are on schedule to have the Miro towers open early 2021.

4 Diller Tops Out Along El Camino Real in Redwood City, CA

Largo topped out at the 4 Diller project in Redwood City, CA this month! The 555,736gsf building is located in the heart of Silicon Valley and 35 of the 350 total units are designated as for affordable housing. The development has three levels of below grade parking which houses 441 private vehicles and 89 bikes. In addition to 2,900sf of retail space at street level the development features a fitness room, a club room and rooftop pool deck. General contractor and developer Greystar, Studio T Sqaure Architects and structural engineer Cary Kopczynski & Company aim to have the development open late 2020.

UCSD North Torrey Pines Living and Learning Center Buildings Three & Four

Largo recently topped out on the North Torrey Pines Living and Learning Center at the University of California, San Diego. The project was designed by HKS Architect, Inc. and Magnusson Klemencic Associates is located on the southeast corner of North Torrey Pines Rd. and Muir College Dr. in La Jolla, CA. Largo’s scope only covered a portion of the overall development with buildings Three and Four consisting of 15 and 14 levels respectively, for a total of 600,000gsf. The development features 2,000 new beds for undergraduate students with related residential life space, new facilities for the Sixth College, social sciences, arts and humanities, dining and retail space, and 1,200 parking stalls. General contractor Clark Construction is aiming to have the development open for the Fall 2020 semester with a LEED Platium rating.

1066 Market Topping Out

Largo topped-out at the 1066 Market street high-rise this week in downtown San Francisco. The building features two levels of below grade parking with 97 total stalls and 4,000sf of retail at grade level. 303 high-end residential units span the following 15 levels above grade. Largo is working with general contractor Swinerton Builders, architect Solomon Cordwell Buenz & Assoc. and structural engineer Nishkian Menninger to have the building open in early 2020.