Clippers Chairman and Inglewood Mayor Celebrate Intuit Dome Topping Out

Clippers’ Chairman Steve Ballmer the mayor of Inglewood James T. Butts visited the construction site to celebrate the topping out milestone.

Largo had placed over 55,000 cubic yards of concrete in just over six months with 213,000 manhours in the three lower levels of the stadium. This scope included 400,000sf of formed deck, 145,000sf of cast-in-place walls and 80,000sf of shotcrete perimeter walls. A total of 497 columns were also cast, some of which stand over 32ft tall from the event level to the Plaza Level.

Learn more about this project.

Related Posts